Contract reference / ODOT
Contract or-15270
SE 129TH AVENUE BIKE LANE AND SIDEWALK
Partial contract coverage. Rank is the bidder’s overall contract bid rank. Neither lowest rank nor source contract number proves award. Project special provisions are not exhaustively reviewed. This is not a complete bid tabulation or final payment record.
Loaded work definitions
- Aggregate Base · 0641-0102000M · Edition unknown
- Level 3, 1/2 Inch ACP Mixture · 0744-0302000M · Edition unknown
Original bid observations
| Item / bid | Quantity | Unit price (USD) | Status / provenance |
|---|---|---|---|
| Aggregate Baseor-15270-rank-1 · line Not published | 2,000short ton | $30.00raw | Overall bid rank 1 · bid-rankedOriginal source · BID DATA, row 2399 ↗ |
| Aggregate Baseor-15270-rank-2 · line Not published | 2,000short ton | $72.00raw | Overall bid rank 2 · bid-rankedOriginal source · BID DATA, row 2400 ↗ |
| Aggregate Baseor-15270-rank-3 · line Not published | 2,000short ton | $32.00raw | Overall bid rank 3 · bid-rankedOriginal source · BID DATA, row 2401 ↗ |
| Aggregate Baseor-15270-rank-4 · line Not published | 2,000short ton | $70.00raw | Overall bid rank 4 · bid-rankedOriginal source · BID DATA, row 2402 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15270-rank-1 · line Not published | 1,400short ton | $105.00raw | Overall bid rank 1 · bid-rankedOriginal source · BID DATA, row 2403 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15270-rank-2 · line Not published | 1,400short ton | $81.00raw | Overall bid rank 2 · bid-rankedOriginal source · BID DATA, row 2404 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15270-rank-3 · line Not published | 1,400short ton | $110.00raw | Overall bid rank 3 · bid-rankedOriginal source · BID DATA, row 2405 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15270-rank-4 · line Not published | 1,400short ton | $125.00raw | Overall bid rank 4 · bid-rankedOriginal source · BID DATA, row 2406 ↗ |
Official contract source ↗ · Why rank does not establish an award