Item / bidQuantityUnit price (USD)Status / provenance
Cold Plane Pavement Removal, 2 Inches Deepor-15478-rank-1 · line Not published850square yard$9.45rawOverall bid rank 1 · bid-rankedOriginal source · BID DATA, row 7870 ↗
Cold Plane Pavement Removal, 2 Inches Deepor-15478-rank-2 · line Not published850square yard$13.00rawOverall bid rank 2 · bid-rankedOriginal source · BID DATA, row 7871 ↗
Cold Plane Pavement Removal, 2 Inches Deepor-15478-rank-3 · line Not published850square yard$14.50rawOverall bid rank 3 · bid-rankedOriginal source · BID DATA, row 7872 ↗
Aggregate Baseor-15478-rank-1 · line Not published500short ton$69.25rawOverall bid rank 1 · bid-rankedOriginal source · BID DATA, row 7881 ↗
Aggregate Baseor-15478-rank-2 · line Not published500short ton$64.00rawOverall bid rank 2 · bid-rankedOriginal source · BID DATA, row 7882 ↗
Aggregate Baseor-15478-rank-3 · line Not published500short ton$97.00rawOverall bid rank 3 · bid-rankedOriginal source · BID DATA, row 7883 ↗
Level 3, 1/2 Inch ACP Mixtureor-15478-rank-1 · line Not published675short ton$170.00rawOverall bid rank 1 · bid-rankedOriginal source · BID DATA, row 7884 ↗
Level 3, 1/2 Inch ACP Mixtureor-15478-rank-2 · line Not published675short ton$170.00rawOverall bid rank 2 · bid-rankedOriginal source · BID DATA, row 7885 ↗
Level 3, 1/2 Inch ACP Mixtureor-15478-rank-3 · line Not published675short ton$193.00rawOverall bid rank 3 · bid-rankedOriginal source · BID DATA, row 7886 ↗