- Level 3, 1/2 Inch ACP Mixture · 0744-0302000M · 2024
Original bid observations
| Item / bid | Quantity | Unit price (USD) | Status / provenance |
|---|---|---|---|
| Level 3, 1/2 Inch ACP Mixtureor-15530-rank-1 · line Not published | 60short ton | $240.00raw | Overall bid rank 1 · bid-rankedOriginal source · BID DATA, row 14754 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15530-rank-2 · line Not published | 60short ton | $375.00raw | Overall bid rank 2 · bid-rankedOriginal source · BID DATA, row 14755 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15530-rank-3 · line Not published | 60short ton | $465.00raw | Overall bid rank 3 · bid-rankedOriginal source · BID DATA, row 14756 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15530-rank-4 · line Not published | 60short ton | $400.00raw | Overall bid rank 4 · bid-rankedOriginal source · BID DATA, row 14757 ↗ |
| Level 3, 1/2 Inch ACP Mixtureor-15530-rank-5 · line Not published | 60short ton | $450.00raw | Overall bid rank 5 · bid-rankedOriginal source · BID DATA, row 14758 ↗ |